Exam PRF topic 1 question 5 discussion

Actual exam question from BCS's PRF
Question #: 5
Topic #: 1
[All PRF Questions]

How many tasks does the product-based planning technique describe?

  • A. One
  • B. Two
  • C. Three
  • D. Four
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
siahpoosh
2 years, 10 months ago
The Product Based Planning Technique consists of four steps: 1.Create a Project Product Description for the project final product (used for Project Plan only) 3.Create the Product Breakdown Structure 3.Create a Product Description for each lower level product 4.Create a Product Flow Diagram
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...