Exam N10-007 topic 1 question 96 discussion

Actual exam question from CompTIA's N10-007
Question #: 96
Topic #: 1
[All N10-007 Questions]

A company has contracted with an outside vendor to perform a service that will provide hardware, software, and procedures in case of a catastrophic failure of the primary datacenter. The Chief Information Officer (CIO) is concerned because this contract does not include a long-term strategy for extended outages. Which of the following should the CIO complete?

  • A. Disaster recovery plan
  • B. Business continuity plan
  • C. Service level agreement
  • D. First responder training
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
simo77
2 years, 1 month ago
A business continuity plan (BCP) is a document that outlines how a business will continue operating during an unplanned disruption in service. ... Plans may provide detailed strategies on how business operations can be maintained for both short-term and long-term outages. B is correct
upvoted 1 times
...
BarkingSpider
2 years, 4 months ago
But if the BCP isn't in place, then perhaps it was never included in the SLA from the service provider, hence the SLA should be addressed to INCLUDE a BCP.
upvoted 2 times
...
vorozco
2 years, 7 months ago
Answer is B. Business continuity plan "If the disaster requires actions offsite from the primary infrastructure, it is under the jurisdiction of business continuity." The key phrase in this question is "contracted with an outside vendor." Disaster recovery involves "getting the IT infrastructure up and running at the primary business location(s)." This is not what is happening in this scenario. -Mike Meyers, Network+ Certification Exam N10-006, pg. 642
upvoted 2 times
...
Ty_tyy
2 years, 10 months ago
jason dion.. OBJ-3.2: A business continuity plan (BCP) is a plan to help ensure that business processes can continue during a time of emergency or disaster. Such emergencies or disasters might include a fire or any other case where business cannot occur under normal conditions. A disaster recovery plan is useful (and usually a piece of the large business continuity plan), but it is insufficient for the long-term strategy which is needed to support business operations during an extended outage.
upvoted 3 times
...
Skitzo
3 years, 4 months ago
I think you're right. Disaster recovery is about how to put it back to normal, Business continuity is how to keep the business going when a disaster strikes.
upvoted 4 times
Ejjaba
3 years, 2 months ago
DR is short term; recovering from a disaster in a matter of days if not hours. BCP is long term; how to continue business over a period of months. COVID is a good example here. DR would be working in smaller shifts and limiting how many people are working in close proximity. BCP would be beefing up the VPN and setting employees up to work remote.
upvoted 1 times
...
...
Asong01
3 years, 4 months ago
The trick here is "long-term strategy"---------------------This makes option A most correct.
upvoted 3 times
Asong01
3 years, 3 months ago
My bad guys. I meant to say the correct answer is B
upvoted 6 times
ay_caramba24
3 years ago
We know <3
upvoted 3 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...