Exam PK0-004 topic 1 question 316 discussion

Actual exam question from CompTIA's PK0-004
Question #: 316
Topic #: 1
[All PK0-004 Questions]

Given the information in the table below, which of the following is the total project cost?

  • A. $40,000
  • B. $70,000
  • C. $95,000
  • D. $120,000
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
SamEsther
Highly Voted 2 years, 10 months ago
$70000 is correct! CEO Bonus and new executive admin are not part of the total project cost!
upvoted 7 times
...
SQLDON
Most Recent 2 years, 11 months ago
can someone explain why 70000 and not 120000 please?
upvoted 1 times
...
l0609890
3 years ago
shouldn't all these components be considered as project costs? I going to stick with 120,000 unless someone can point out that some of the components shouldn't be considered.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...