Exam PK0-004 topic 1 question 94 discussion

Actual exam question from CompTIA's PK0-004
Question #: 94
Topic #: 1
[All PK0-004 Questions]

A senior manager asks a project manager for an estimated budget on a new project.
Which of the following is the BEST step for the project manager to take?

  • A. Tell the senior manager the estimation is not available yet.
  • B. Use the budget from a similar project to generate estimates.
  • C. Ask a SME for an opinion and propose an estimate.
  • D. Gather the team to immediately generate estimates.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 164

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
boooliyooo
2 years, 1 month ago
B is likely better as SME is most likely to be someone who is good at a subset of a whole project
upvoted 1 times
...
EveryDayImStruggling
2 years, 7 months ago
I'd think the SME would be more task focused rather than big picture. They'd know more of how specific tasks should go instead of total project costs.
upvoted 2 times
...
dyers
2 years, 8 months ago
I'm not exactly following how this is the BEST answer, for example, using a SME will get the most accurate estimate, taking a similar project gives the least accurate estimate. What criteria makes you choose B?
upvoted 2 times
PenguPC
2 years, 6 months ago
The only answer I can come up with is that this is a question about analogous estimating.
upvoted 1 times
brown705
1 year, 9 months ago
Taken from pg 149 in my copy of Heldman (which doesn't line up with what is reported as reference, ever): "Analogous estimating will likely be the best technique to use at the early stage of the project because you’ll have very little detail to go on."
upvoted 1 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...