A project manager is performing resource leveling and notices one of the functional testers is assigned 40% in a second project. The project manager needs the resource to be 100% dedicated to the project; otherwise, the testing phase jeopardizes the delivery date. Which of the following should the project manager do
NEXT?
Orby
1 year, 3 months agocatastrophie
1 year, 11 months agoTreymb6
2 years agoHanzoShimada
2 years ago