Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.
A Development Team consists of various different roles: analysts, programmers, UX experts, DBA and systems architects. They are estimating Backlog Items in Ideal Days. What is the best approach to provide estimates for the Backlog Items?
A.
Each role should provide a separate estimate; the Scrum Master integrates them.
B.
Ideal days' estimation is not feasible in this case; Story Points should be used.
C.
The Development Team provides a single estimate for each Backlog Item.
D.
The Product Owner will integrate the input on the estimates from each role.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
foxpro7
2 years, 8 months agokschinchin
2 years, 10 months ago