Exam CSM-001 topic 1 question 32 discussion

Actual exam question from GAQM's CSM-001
Question #: 32
Topic #: 1
[All CSM-001 Questions]

What is the primary objective of the daily scrum?

  • A. To share with the team what each member has completed in the Sprint, what each member will work on next, and to report progress roadblocks
  • B. To give a status report to the Product Owner on what each member has completed in the Sprint, what each member will work on next, and to report progress roadblocks.
  • C. To discuss work details with the team since every team member must attend the meeting
  • D. To give a status report to the Scrum Master on what each member has completed in the Sprint, what each member will work on next, and to report progress roadblocks.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
patitos
1 year, 12 months ago
Answer is A
upvoted 1 times
...
aktheraja
3 years, 11 months ago
A: share
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel