Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam C2010-555 topic 1 question 19 discussion

Actual exam question from IBM's C2010-555
Question #: 19
Topic #: 1
[All C2010-555 Questions]

A master PM can be used to do which of the following?

  • A. Create a job plan revision.
  • B. Generate work orders for associated PMs.
  • C. Create associated PMs for an item's location.
  • D. Change the status of work orders generated from associated PMs.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
Reference:
http://www.redbooks.ibm.com/redbooks/pdfs/sg247761.pdf
(page 55)

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
dlp
2 years, 11 months ago
Assets, not items, are associated with Locations. Poorly worded and misleading.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...