Question #: 43
Topic #: 4
[All IIA-CIA-Part2 Questions]

Which of the following is correct with respect to roles within an enterprise-wide risk management process?
1. The board provides oversight to the risk management process.
2. Executive management owns the risk management framework.
3. Senior management is assigned ownership of risks.
4. Internal audit modifies the risk assessment determined by management.

  • A. 1 and 2 only
  • B. 3 and 4 only
  • C. 1, 2, and 3 only
  • D. 1, 2, 3, and 4
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
KonradK
2 years, 8 months ago
C is incorrect as SM are not risk owners. I think A is the correct answer.
upvoted 1 times
...
herdintche
2 years, 10 months ago
Risklerin sahibi olan, üst yönetim midir yönetim midir?
upvoted 1 times
...
Tico
3 years, 2 months ago
Why not A? "ownership of risks" means a risk owner, doesn't it? If so, senior management is not a risk owner.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...