Exam CBAP topic 1 question 121 discussion

Actual exam question from IIBA's CBAP
Question #: 121
Topic #: 1
[All CBAP Questions]

You are the business analyst for your organization and are working with Ralph who is also a business analyst at your company. You have moved one of the requirements higher in the prioritization of the requirements because it is needed to be implemented before some of the more important requirements are done.
Ralph disagrees with your placement of the requirement because you are to rank the requirements based on their level of difficulty.
Who is correct and why?

  • A. Ralph is correct because the requirements are always to be ranked by importance or business value.
  • B. You are correct because the lower priority requirements must be completed before the higher priority requirements can be done.
  • C. You are correct because you are the senior business analyst.
  • D. Ralph is correct because the sequence of requirements is actually done with the project activity list.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
mountaingoat
Highly Voted 3 years, 3 months ago
A is the right answer
upvoted 8 times
QE
3 years, 1 month ago
Could you please explain why A is the right answer? This seem like the higher requirements depends on the lower requirements, thus they have to be implemented. Page 82.
upvoted 4 times
...
...
Ray81
Highly Voted 3 years, 1 month ago
B cannot be correct, because order of priority means that requirements with higher priority should be implemented first, not the other way round
upvoted 5 times
Nekdre
2 years, 2 months ago
I agree the lower priority ones can't be done first, higher priorities are done first so I will choose A because priority is more on the business value
upvoted 2 times
...
...
SaintTC
Most Recent 2 months, 1 week ago
Answer A - 5.3.2
upvoted 1 times
...
csg2023
2 months, 2 weeks ago
B is correct. The higher priority requirement depends on the lower one hence the lower one has to be implemented first
upvoted 2 times
...
Rfcuenca
3 months ago
Option B Dependencies between requirements: Some capabilities may in and of themselves provide limited value to the organization, but need to be delivered in order to support other high-value requirements. Babok v2.- Page 126
upvoted 2 times
...
Mari1403
5 months ago
Selected Answer: B
Higher difficulty requirement is dependent on the lower difficulty one.
upvoted 1 times
...
Sha7rour
1 year, 6 months ago
Answer is B, but the funny thing here is that the question shows that the BAs cant understand each other. it is clear that higher req depends on the lower req so the lower should go first.
upvoted 2 times
...
cake12345
1 year, 10 months ago
The ranking of the requirements based on their level of difficulty is fine, but you may also include a requirement's relationship to other requirements. If higher priority requirements cannot be completed until the lower priority requirements are done, then the requirements should be ordered as such for the order of implementation.
upvoted 1 times
...
Spartanxxv
1 year, 11 months ago
Selected Answer: B
The higher priority requirement is dependent on the lower priority requirement.
upvoted 2 times
...
OlivierPaudex
2 years, 1 month ago
I think answer B is correct. We are talking about a requirement you moved in a higher position, to be implemented first. The lower requirement (the requirement you just moved to a higher position) should be done first. Question is a bit confusing cause it says that Ralph is disagree and you have to explain him that you move a lower requirement to an higher position, so that it can be done first. High requirements are done first and that is exactly what you have done by moving a low priority to high.
upvoted 3 times
...
SamiAbuQurs
2 years, 3 months ago
Answer is B since "Dependencies" is one of the factors that influence prioritization. BABOK v3 : Prioritize Requirements 5.3.4
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...