A business analyst (BA) is reviewing the performance results from a recent change initiative. One of the results stated, "The planned schedule expected 50% of the project to be done at milestone 6. The schedule performance index (SPI) was .87. Three project team members worked overtime to ensure that the actual schedule would align with the planned schedule."
This is an example of what type of action?