Exam CBAP topic 1 question 459 discussion

Actual exam question from IIBA's CBAP
Question #: 459
Topic #: 1
[All CBAP Questions]

A business analyst (BA) is assigned a new project to improve a delivery process. Which of the following does the BA create as an output of the initial meeting with experts?

  • A. Information management approach
  • B. Elicitation activity plan
  • C. Entity relationship diagram
  • D. Current state flowchart
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
rhsdeal
Highly Voted 2 years, 11 months ago
Ans is B: BABOK V-3 6.1.2 Analyze Current State - The starting point for any change is an understanding of why the change is needed. Potential change is triggered by problems or opportunities that cannot be addressed without altering the current state. 6.1.3 Inputs: Elicitation Results- used to define and understand the current state. 4.1.8 Prepare for Elicitation: Outputs - • Elicitation Activity Plan: used for each elicitation activity. It includes logistics, scope of the elicitation activity, selected techniques, and supporting materials.
upvoted 7 times
...
binu801
Highly Voted 2 years, 7 months ago
Ans D- experts is the keyword. expert will help to understand the current process
upvoted 5 times
...
Rabbitsfoot
Most Recent 19 hours, 9 minutes ago
Selected Answer: D
In the initial meeting with experts to improve a delivery process, the business analyst (BA) typically focuses on understanding the existing process. Creating a current state flowchart helps the BA document how the process currently operates, including all the steps, inputs, outputs, and decision points involved. This visualization provides a clear picture of the current workflow, which serves as a basis for identifying areas of improvement and formulating strategies for the future state. Therefore, creating a current state flowchart is an essential output of the initial meeting to establish a starting point for the analysis and improvement efforts.
upvoted 1 times
...
DFU
3 months, 4 weeks ago
Selected Answer: B
Review the stakeholders for both Prepare for Elicitation and Analyze Current State and you will see the former has just three persons ( Sponsor, PM & Domain SME) while the later has different categories of stakeholders including customers). Also review the guidelines and tools as a way of confirming that the choice is Elicitation Activity Plan.
upvoted 1 times
...
[Removed]
6 months, 1 week ago
Selected Answer: B
Elicitation Result is an input to Analyze Current State Elicitation Results: used to define and understand the current state. (p103) So, we need to conduct elicitation first and for this to have Elicitation Activity Plan
upvoted 1 times
...
xiaoyangwu
6 months, 1 week ago
Selected Answer: D
Actually I think it should be "business analysis approach", but no this option. so choose current state description
upvoted 1 times
...
Wolfedale
1 year, 11 months ago
Selected Answer: D
D - Current State Expert Judgement is a guideline and tool in Plan Business Analysis Approach (v3 3.1.5) Current State Description is a guideline and tool in the following Plan Stakeholder Engagement (v3 3.2.5)
upvoted 2 times
...
OlivierPaudex
2 years ago
agree with this comment. You have to elicit stakeholders to know more about the current state. Have a meeting with experts could be considered as an elicitation. You can therefore begin to design through a flowchart
upvoted 1 times
...
ccie_cbap
2 years, 9 months ago
Ans D- Current state. Please understand. When a BA is starting on a new project, he/she must 'Assess current state'.
upvoted 3 times
Mmotun
1 year, 10 months ago
Look at analyse current state. Elicitation results is an input
upvoted 1 times
...
...
[Removed]
2 years, 9 months ago
Ans. D- Current State Flow Chart. 'Elicitation Activity Plan' is an output of the task - 'Prepare for Elicitation'. This question is about the output from Conduct elicitation task. Pg 103. Analyze Current State - The starting point for any change is an understanding of why the change is needed. Creating a model of the current state might require collaboration throughout or outside the enterprise. In Pg. 318 - The business analyst can use a process model to define the current state of a process (also known as an as-is model) or a potential future state (also known as a to-be model) and flow chart is a type of process mode.
upvoted 4 times
...
rupakarthik
2 years, 11 months ago
Ans-D The starting point for any change is an understanding of why the change is needed. Potential change is triggered by problems or opportunities that cannot be addressed without altering the current state.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel