Question #: 97
Topic #: 1
[All CBAP Questions]

You are the business analyst for your organization. Management has asked that in the business case you're creating that you also include the projected costs and benefits to be realized and how those and benefits will be assessed and evaluated.
What term matches management's request?

  • A. Cost-benefits justification
  • B. Risk assessment
  • C. SWOT analysis
  • D. Results measurements
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
moririn
5 months ago
Selected Answer: A
Cost-benefits justification is a process of identifying and assessing the costs and benefits of a proposed project or initiative
upvoted 1 times
...
OlivierPaudex
1 year, 5 months ago
not A, cause the questions asks you to evaluate the costs B and C are out of scope D is the best answer, but it is a BABOK v2 question.
upvoted 1 times
Farooq_95
1 week, 1 day ago
Question asks about term for Management's request, not about technique for evaluation. The management is requesting for cost-benefits justification by asking to include projected costs and benefits. So, correct answer is A
upvoted 1 times
...
...
Fadj
1 year, 9 months ago
I think the answer is A
upvoted 2 times
...
Fedara
1 year, 9 months ago
Same. I would have selected A too
upvoted 2 times
...
ElyonSenjo
1 year, 11 months ago
Selected Answer: A
BABOK v3 ref. technique Business Case
upvoted 3 times
...
MFZZ
2 years, 1 month ago
If this was referring to BABOK v3 I would have selected 'A' pg 275 Question asks what the project cost and benefit would be '... a prediction of the expected total benefits minus the expected total costs, resulting in an expected net benefit (the planned business value).
upvoted 2 times
...
MFZZ
2 years, 2 months ago
This question seems to refer to ok BABOK V2. I really get upset when I see references to this version as I want to apply for an exam referencing v3.
upvoted 4 times
Alwaysmoses
1 year, 9 months ago
same here
upvoted 1 times
...
...
Dillon91
2 years, 3 months ago
Not sure it is D
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...