C. Communication.
A risk heat map is most commonly used as part of an IT risk analysis to facilitate risk "C. Communication." A risk heat map provides a visual representation of risks based on their likelihood and impact, usually using colors to represent different risk levels. This visual representation helps communicate complex risk information in a clear and concise manner, making it easier for stakeholders to understand and prioritize risks.
While risk heat maps can also be used in other stages of risk management, such as identification, assessment, and treatment (options B, D, and A), their primary purpose is to enhance communication of risks to various stakeholders, making option C the most appropriate answer.
D is correct. A risk heat map is a tool used to present the results of a risk assessment process visually and in a meaningful and concise way. Whether conducted as part of a broad-based enterprise risk management process, or more narrowly focused internal control process, risk assessment is a critical step in risk management.
OK. D is incorrect. C is correct as Definition of risk map (risk heat map)
What is a risk map (risk heat map)?
A risk map (risk heat map) is a data visualization tool for communicating specific risks an organization faces. A risk map helps companies identify and prioritize the risks associated with their business.
When a risk heat map is used to represent results of an assessment. Not sure how it facilitate the risk assessment itself. You can complete a risk assessment then use the results to create a heat map. Which can quickly communicate key risk to the organization.
Answer is C. Risk heap map is most useful when communicate Risk to management
upvoted 3 times
...
...
This section is not available anymore. Please use the main Exam Page.CRISC Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Staanlee
10 months, 3 weeks agoKoulyo
1 year, 3 months agoCbtL
1 year, 3 months agojohn_boogieman
1 year, 4 months agojohn_boogieman
1 year, 5 months agoCeecil1959
2 years, 4 months agoCeecil1959
2 years, 4 months agoRaj1510
2 years, 6 months agoAnon530
3 years, 3 months agoNJJ
3 years, 4 months agothedood
3 years, 10 months agopnikoul
3 years, 6 months ago