Actual exam question from ISC's CISSP
Question #: 295
Topic #: 9
[All CISSP Questions]

An organization that has achieved a Capability Maturity Model Integration (CMMI) level of 4 has done which of the following?

  • A. Achieved optimized process performance
  • B. Achieved predictable process performance
  • C. Addressed the causes of common process variance
  • D. Addressed continuous innovative process improvement
Show Suggested Answer Hide Answer

Suggested Answer: A
Reference:
https://www.sciencedirect.com/topics/computer-science/capability-maturity-model-integration

Comments

Mamun
Highly Voted 4 months, 3 weeks ago
B A critical distinction between maturity level 3 and maturity level 4 is the predictability of process performance. Maturity Level 5 Optimizing
upvoted 5 times
...
DigitalDanny
Most Recent 4 days, 2 hours ago
Based on the below levels, answer is clearly B. Maturity Level 1 – Initial. Maturity Level 2 – Managed. Maturity Level 3 – Defined (Predictable) Maturity Level 4 – Quantitatively Managed. 5.Maturity Level 5 – Optimizing
upvoted 1 times
...
MK_Simon
4 days, 8 hours ago
At maturity level 4, processes are quantitatively predictable. At maturity level 3, processes are only qualitatively predictable.
upvoted 1 times
MK_Simon
3 days, 16 hours ago
Answer A is correct as level 4 is the most mature process development before any further innovative advancement. So the statment 'optimized process performance' is applicable.
upvoted 1 times
...
...
kabwitte
1 week, 2 days ago
This is B. We're not there yet
upvoted 1 times
...
MoneyPaper
2 weeks, 6 days ago
Key word supporting B is "Predictable" Managed - quantitative and measurable objectives are established for tasks. Baseline is formed from which assessment is done
upvoted 1 times
...
Ramnik
2 months, 3 weeks ago
B is correct. Maturity Level 4: Quantitatively Managed Organization is data-driven with quantitative performance improvement objectives that are predictable and align to meet the needs of internal and external stakeholders.
upvoted 1 times
...
yoman19
3 months, 1 week ago
Answer is B
upvoted 1 times
...
nohup
4 months, 4 weeks ago
Ans is C
upvoted 1 times
nohup
4 months, 4 weeks ago
Not C, it is B. Ref: https://www.tutorialspoint.com/cmmi/cmmi_quick_guide.htm
upvoted 3 times
...
...
Cissp929
5 months ago
Maturity Level 4: Quantitatively Managed Measured and controlled. Organization is data-driven with quantitative performance improvement objectives that are predictable and align to meet the needs of internal and external stakeholders.
upvoted 3 times
kchoo321
3 months ago
https://cmmiinstitute.com/learning/appraisals/levels
upvoted 1 times
...
...