Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PMI-PBA topic 1 question 90 discussion

Actual exam question from PMI's PMI-PBA
Question #: 90
Topic #: 1
[All PMI-PBA Questions]

A few months into a project, the business analyst determines that the costs are exceeding the perceived benefits. The business analyst wants to address the possible risks of having to cancel the product.
Which of the following documents should be used?

  • A. Stakeholder impact matrix
  • B. Project charter
  • C. Business analysis plan
  • D. Business case
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
giushki
1 year ago
Selected Answer: D
D. Business case should be used to address the possible risks of having to cancel the product if the costs are exceeding the perceived benefits. The business case outlines the justification for the project, including the expected benefits, costs, and risks, and is used to evaluate whether the project is still viable as it progresses.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...