Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
Location Chicago IL, USA

Exam PMI-RMP topic 1 question 195 discussion

Actual exam question from PMI's PMI-RMP
Question #: 195
Topic #: 1
[All PMI-RMP Questions]

You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualitative risk analysis process except for which one?

  • A. Stakeholder register
  • B. Project scope statement
  • C. Risk management plan
  • D. Risk register
Show Suggested Answer Hide Answer

Suggested Answer: A

Comments

cskhal
1 month, 1 week ago
(B) is the right answer
upvoted 1 times
...
WH1212
9 months, 3 weeks ago
I believe the answer must be (A) in this case: as per the PMBOK-6th edition-P 419, the input to Perform Qualitative Risk Analysis is: .1 Project management plan • Risk management plan .2 Project documents • Assumption log • Risk register • Stakeholder register .3 Enterprise environmental factors .4 Organizational process assets
upvoted 1 times
...

SaveCancel