Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?
process MANAGE STAKEHOLDER ENGAGEMENT OUTPUT
1 Change requests
.2 Project management plan
updates
• Communications
management plan
• Stakeholder engagement
plan
.3 Project documents updates
• Change log
• Issue log
• Lessons learned register
• Stakeholder register