Actual exam question from PMI's PgMP
Question #: 382
Topic #: 1
[All PgMP Questions]

Component project managers create project management plans for all component projects in a program. The program manager notices that some project managers prefer one status report template, while others prefer another.
How should the program manager decide which template is appropriate?

  • A. Review the issue with the program management office (PMO) to determine which template to use.
  • B. Review the issue with the project managers and come to mutual agreement on which template to use.
  • C. Meet with the program governance board to select an appropriate template.
  • D. Allow the component project managers to use their preferred templates.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
[Removed]
4 months, 1 week ago
Selected Answer: A
A. Review the issue with the program management office (PMO) to determine which template to use. The PMO is responsible for standardizing processes across programs, which would include standardization of status report templates. By involving the PMO, the program manager can ensure that the chosen template aligns with the organization's governance practices and provides consistency in reporting across all component projects within the program. The PMO's role in professional expertise and decision-making support would be critical in resolving the issue of differing preferences for status report templates among project managers.
upvoted 1 times
...
hanyulin
4 months, 2 weeks ago
Selected Answer: A
A is the right answer.
upvoted 2 times
...
ekk1983
5 months, 2 weeks ago
A what I picked
upvoted 1 times
...
NawrasHamwi
1 year, 3 months ago
Selected Answer: A
A, is more logic answer
upvoted 1 times
...
snow5
2 years, 11 months ago
The program management office (PMO) is a key stakeholder on programs. It provides support to individual program teams or program managers by dealing with administrative issues centrally, and it defines and manages program-related governance processes, procedures, templates, and so on. PMI®, The Standard for Program Management, 2008, 235
upvoted 1 times
...
snow5
3 years ago
A is more logic
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...