Exam PgMP topic 1 question 364 discussion

Actual exam question from PMI's PgMP
Question #: 364
Topic #: 1
[All PgMP Questions]

In a program's definition phase, a program manager in country A is assigned to expand a restaurant chain into country B. The program manager creates the program team by identifying the required project management resources.
Which of the following represents an initial step needed to evaluate available resources that are aligned with the program's needs?

  • A. Completing an assessment of skills and competencies
  • B. Obtaining resource availability information from the functional managers
  • C. Identifying program resource requirements
  • D. Creating a program resource management plan
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
happykaur
1 month, 4 weeks ago
Selected Answer: C
8.1.1.3
upvoted 1 times
...
hanyulin
3 months ago
Selected Answer: A
the question asked in step 2, "to evaluate available resources" measured complete step 1.
upvoted 1 times
...
happykaur
3 months, 1 week ago
Selected Answer: C
In the program's definition phase, where the program manager is tasked with expanding a restaurant chain into a new country and needs to evaluate available resources that are aligned with the program's needs, an initial step would be: C. **Identifying program resource requirements** This step involves defining the types of resources (human, technical, financial, etc.) required for the program, based on the program's objectives and scope. It sets the foundation for further steps like assessing skills, obtaining availability information, and developing a resource management plan.
upvoted 1 times
...
hanyulin
4 months ago
Selected Answer: C
C is the right answer.
upvoted 2 times
...
[Removed]
4 months ago
Selected Answer: C
C. Identifying program resource requirements. This step involves defining what types of resources (human resources, equipment, materials, etc.) are needed, along with the specific skills, competencies, and quantities required for the successful execution of the program. By clearly identifying the resource requirements, the program manager can then proceed to assess the availability and suitability of resources within the organization or determine the need to acquire resources externally.
upvoted 1 times
...
chaoman
2 years, 4 months ago
C & D are outputs of program resources management and B is the first step to identify available resources.
upvoted 1 times
...
Corners
2 years, 11 months ago
C. Firstly you have to develop resource requirements, who do you need at all. Then availability of the resources and skills assessments.
upvoted 1 times
...
tsangckl
2 years, 11 months ago
B is correct. As you need to have available resources to evaluate or access. B first and then A.
upvoted 2 times
...
snow5
2 years, 11 months ago
A is the right answer, skill assessment is the first step
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...