A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.
What should the project manager do next?
[Removed]
Highly Voted 3 months, 2 weeks agokdanthuri
2 months, 2 weeks agoHao2
Highly Voted 11 months, 2 weeks agoAcumen88
9 months, 3 weeks agoDMHR
Most Recent 2 months, 1 week agoBuviD
2 months, 3 weeks agovshreevj13
5 months, 3 weeks agoRavi4french
5 months, 3 weeks agoRaymond1105
6 months, 1 week agokakahoanghuy
6 months, 2 weeks agonemm235
6 months, 2 weeks agolan_think
6 months, 3 weeks agoAlphy07
6 months, 4 weeks agorockylee
7 months agoitvanthong87
7 months agoMahi_02021988
7 months, 3 weeks agoEmmyomy
8 months agoMbolatiana
8 months, 2 weeks agoNitindb
9 months, 1 week ago