Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PMP topic 1 question 1 discussion

Actual exam question from PMI's PMP
Question #: 1
Topic #: 1
[All PMP Questions]

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.
What should the project manager do next?

  • A. Consult the risk register for an appropriate planned risk response and implement.
  • B. Revise the project management plan and move the task to a time when the technical resource will be available.
  • C. Review the business requirement with stakeholders and exclude the task assigned to the technical resource.
  • D. Update the lessons learned report and the risk log to reflect that this risk has materialized.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
[Removed]
Highly Voted 3 months, 2 weeks ago
I wrote my exams on nov 28th and scored above target for all the sections. About 80% of the questions are from the last pages so please start from the back and solve about 500 questions and you will be fine. The new questions are very easy to answer if you have read the itexamslab.com or any material you used. In all, the exams is not as scary as they make it look like..all the best to anyone writing
upvoted 31 times
kdanthuri
2 months, 2 weeks ago
Hi, Congratulations! could you please tell me how to do get access to all the questions. thank you.
upvoted 1 times
...
...
Hao2
Highly Voted 11 months, 2 weeks ago
Selected Answer: A
Hint is PM already identified this risk during Project Planning. Output of Identify Risk process is Risk register. Basically, a good PM w/ 4 values & 12 principles under PMI languages need to do this task with due diligent thus Risk register can be used later as sufficient reference regarding risk response plan when relevant risk happen. A is still the correct answer.
upvoted 19 times
Acumen88
9 months, 3 weeks ago
Considering that the risk has been identified during project planning, the PM needs to consult the risk register to ascertain if there is a response to this risk. The answer is A.
upvoted 1 times
...
...
DMHR
Most Recent 2 months, 1 week ago
ANSWER - A
upvoted 1 times
...
BuviD
2 months, 3 weeks ago
Selected Answer: A
A. Consult the risk register for an appropriate planned risk response and implement.
upvoted 1 times
...
vshreevj13
5 months, 3 weeks ago
A. Consult the risk register for an appropriate planned risk response and implement.
upvoted 1 times
...
Ravi4french
5 months, 3 weeks ago
Selected Answer: A
stake holders should be informed with updates
upvoted 1 times
...
Raymond1105
6 months, 1 week ago
Selected Answer: A
B,C,D do not make sense, filtered A
upvoted 1 times
...
kakahoanghuy
6 months, 2 weeks ago
Answer is A
upvoted 1 times
...
nemm235
6 months, 2 weeks ago
Q1 - A
upvoted 1 times
...
lan_think
6 months, 3 weeks ago
Selected Answer: A
answer A
upvoted 1 times
...
Alphy07
6 months, 4 weeks ago
The answer is A
upvoted 1 times
...
rockylee
7 months ago
Selected Answer: A
The answer is A
upvoted 1 times
...
itvanthong87
7 months ago
Selected Answer: A
Risk response
upvoted 1 times
...
Mahi_02021988
7 months, 3 weeks ago
Answer is A
upvoted 1 times
...
Emmyomy
8 months ago
Selected Answer: A
Consulting the risk register for risk response plan
upvoted 1 times
...
Mbolatiana
8 months, 2 weeks ago
Selected Answer: A
is my choice
upvoted 2 times
...
Nitindb
9 months, 1 week ago
Selected Answer: A
A is right
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...