Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PMP topic 1 question 8 discussion

Actual exam question from PMI's PMP
Question #: 8
Topic #: 1
[All PMP Questions]

During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.
What should the project manager do next?

  • A. Request the scrum team to prioritize the product backlog
  • B. Ask the product owner to prioritize the backlog with the project team
  • C. Call for an internal meeting to discuss the changes and their value
  • D. Incorporate the changes in the last sprint before the first release
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
psvexam
Highly Voted 6 months, 2 weeks ago
Ans B: Whoever answered C (almost 50% of the lot), if you accept this as the answer, that means you are accepting that any changes can be made during a sprint, and everytime, you just call for a meeting and understand the changes. I dont think this is a good way of conducting a project, whether it is agile or traditional. Though none of the choices are really accurate, probably B is the best bet in this case. Just have the PO work closely with the team and prioritize. Even that also is not a correct answer. Because PO can be prioritizing with team, and still changes may be coming. Issue is how to reduce that to happen. And that is not given in any option.
upvoted 8 times
rahulanand84
6 months, 1 week ago
I feel the same. If you call the team and discuss, the work is already taken as a part of the sprint, which means other things will be delayed. Talking to the PO and prioritizing it is the best way to manage such situations otherwise this would keep happening.
upvoted 2 times
...
...
Aish_
Highly Voted 8 months, 3 weeks ago
Selected Answer: C
As a project manager, the first step should be to hold an internal meeting with the team to discuss their frustrations and concerns regarding the continuous addition of mandatory features mid-sprint. After understanding the team's frustration and concerns, the project manager should then schedule a meeting with the Product Owner. During this meeting, the project manager should share the team's feedback and concerns and discuss the impact of adding mandatory features mid-sprint on the project's success and timeline.
upvoted 6 times
...
Manicks
Most Recent 4 days, 20 hours ago
Ans B: Product owner should prioritize in the backlog in the sprint to bring up the team's confidence and avoid delay.
upvoted 1 times
...
vinuuvasu
1 month, 1 week ago
B. Ask the product owner to prioritize the backlog with the project team In an agile project, the product owner is responsible for prioritizing the product backlog. When mandatory features are frequently added during sprints, it is essential to work with the product owner to reprioritize the backlog and avoid disrupting the team's progress
upvoted 1 times
...
honidt
1 month, 3 weeks ago
Selected Answer: B
B is correct
upvoted 1 times
...
Davard
3 months ago
Selected Answer: B
This aligns with agile principles. It encourages collaboration and transparency between the product owner and the project team. By involving the project team in the prioritization process, it ensures a shared understanding of the priorities and helps manage expectations.
upvoted 2 times
...
BuviD
3 months, 2 weeks ago
Selected Answer: B
B. Ask the product owner to prioritize the backlog with the project team
upvoted 1 times
...
BuviD
3 months, 2 weeks ago
Selected Answer: D
D. Incorporate the changes in the last sprint before the first release
upvoted 1 times
...
Mamoonpk
5 months ago
Selected Answer: B
Product owner to prioritize the backlog. This is the root cause
upvoted 1 times
...
David983
5 months, 1 week ago
Selected Answer: C
The question is talking about include a new mandatory activity in the current Sprint, not to include it into the product backlog. This Iteration change must be evaluated and discussed considering the value and the impact on the sprint. Option C.
upvoted 2 times
...
Only12go
5 months, 4 weeks ago
Selected Answer: B
Given the context that there have been repeated issues in the previous two sprints resulting in failures and team frustration, the best option is B: "Ask the product owner to prioritize the backlog with the project team." This approach directly addresses the root cause of the problem by promoting collaboration between the product owner and the team. When changes are continuously introduced, it's essential to reprioritize the backlog to ensure alignment with the project's goals and to manage the team's capacity effectively. Engaging the team in this process will provide clarity, reduce uncertainties, and help in setting realistic expectations, thereby reducing the chances of future sprint failures and alleviating team frustrations.
upvoted 2 times
...
rahulanand84
6 months, 1 week ago
B. Best way to manage such urgent calls is to have a discussion and prioritize with the PO. If you call the team and discuss, this means the work is already taken in the middle of the sprint, which will delay other things team might have half worked. This would result frustration.
upvoted 1 times
...
vshreevj13
6 months, 1 week ago
C. Call for an internal meeting to discuss the changes and their value
upvoted 1 times
...
Ravi4french
6 months, 2 weeks ago
Selected Answer: C
C. Call for an internal meeting to discuss the changes and their value
upvoted 1 times
...
shivnand
6 months, 3 weeks ago
Option B, asking the product owner to prioritize the backlog with the project team, promotes collaboration and ensures that everyone is on the same page regarding the priorities and the impact of adding new features. It also allows for a more balanced and informed decision-making process, reducing frustration and enhancing project success.
upvoted 1 times
...
Neduone
7 months, 1 week ago
Selected Answer: C
correct answer C
upvoted 1 times
...
Goku_PMP
7 months, 1 week ago
No changes are allowed during iteration.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...