A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.
What should the project manager do?
WhiteTable
Highly Voted 7 months agosheilawu
3 weeks, 4 days agovinuuvasu
Most Recent 2 weeks, 5 days agorarehunter5
3 weeks, 1 day agoBuviD
2 months, 3 weeks agoTony210
4 months, 1 week agoMamoonpk
4 months, 1 week agoziyaetuk
5 months agoestimater
5 months agoRavi4french
5 months, 3 weeks agoshivnand
6 months agoNelsned
6 months, 3 weeks agoAlphy07
6 months, 4 weeks agoAmope
7 months, 2 weeks agokachi007
7 months, 3 weeks agoMahi_02021988
7 months, 3 weeks agoAish_
8 months agoMbolatiana
8 months, 2 weeks ago