B.
To be following PRINCE2, a project must, as a minimum:
•define its approach to controlling progress in the PID
•be managed by stages (PRINCE2’s manage by stages principle)
•set tolerances and be managed by exception against them (PRINCE2’s manage by exception principle)
•review the business justification when exceptions are raised (PRINCE2’s continued business justification principle)
•learn lessons (PRINCE2’s learn from experience principle).