Question #: 436
Topic #: 1
[All PRINCE2-Foundation Questions]

Which control must be used as a minimum requirement for applying the ‘progress’ theme?

  • A. A project plan
  • B. Tolerances
  • C. An issue register
  • D. Highlight reports
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ameli8222
1 year ago
Selected Answer: B
B. To be following PRINCE2, a project must, as a minimum: •define its approach to controlling progress in the PID •be managed by stages (PRINCE2’s manage by stages principle) •set tolerances and be managed by exception against them (PRINCE2’s manage by exception principle) •review the business justification when exceptions are raised (PRINCE2’s continued business justification principle) •learn lessons (PRINCE2’s learn from experience principle).
upvoted 1 times
...
Darkvirusk
1 year, 1 month ago
Selected Answer: D
Tolerances is not a control
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...