C - A change budget should fund an agreed change to a project's scope. A change budget is a set amount of money that a customer and supplier agree to use to cover the costs of requests for change
A change budget is typically allocated to fund changes that have been formally agreed upon and approved, including changes to the project scope. These changes go beyond the initial plan and require additional resources, thus needing specific budget allocation