Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.
Businecc case "define the management actions that will be put in place to ensure that the project’s outcomes are achieved and confirm that the project’s benefits are realized "
The answer should be Business Case, as really the dis-benefits are outcomes which are perceived as negative and are recorded in the Business Case. Business Case is both a theme and a product. Reference 6.2 prince manual:
PRINCE2 requires that two products are produced and maintained for the business case theme:
• B s ness .ase Provides the costs, benefits, expected dis-benefits, risks and timescales against which viability is justified and continuing viability is tested.
It is acceptable to use an alternative document such as a corporate business plan to replace the business case for part of the project lifecycle.
Be e s anag men approacn Defines the management actions that will be put in place to ensure that the project's outcomes are achieved and confirm that the project's benefits are realized.
The correct answer is B : Business Case.
Please refer to section A.2.2. of Appendix A ("Managing successful projects with PRINCE2"):
"Expected dis-benefits The impact of one or more outcomes of the project might be perceived as negative by one or more stakeholders. Dis-benefits are actual consequences of an activity whereas, by definition, a risk is uncertain and may never materialize. For example, a decision to merge two elements of an organization onto a new site may have benefits (e.g. better joint working), costs (e.g. expanding one of the two sites) and dis benefits (e.g. drop in productivity during the merger). Dis-benefits need to be valued and incorporated into the investment appraisal."
Answer B sounds more logical:
"...so the Project Board can be asking “how are we doing compared to the original project plan?”
https://prince2.wiki/management-products/plan/
The correct answer is A : Business Case.
Please refer to section A.2.2. of Appendix A ("Managing successful projects with PRINCE2"):
"Expected dis-benefits The impact of one or more outcomes of the project might be perceived as negative by one or more stakeholders. Dis-benefits are actual consequences of an activity whereas, by definition, a risk is uncertain and may never materialize. For example, a decision to merge two elements of an organization onto a new site may have benefits (e.g. better joint working), costs (e.g. expanding one of the two sites) and dis benefits (e.g. drop in productivity during the merger). Dis-benefits need to be valued and incorporated into the investment appraisal."
D. Project product description. It contains customer quality expectations and acceptance criteria.
I understand that buisiness case needs to be updated if negative outcomes realized - but the description what is perceived as a negative outcome sounds more like product description.
The justification for an organizational activity (project), which typically contains costs, benefits, risks and
timescales, and against which continuing viability is tested.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
peppe
2 years, 6 months agopeppe
2 years, 6 months agoMartin77
2 years, 11 months agotheotenis
2 years, 11 months agotheotenis
2 years, 11 months agovladwerewolf
3 years agovladwerewolf
3 years agoFarbod
3 years, 1 month agotheotenis
2 years, 11 months agotheotenis
2 years, 11 months agohobokabobo
3 years, 9 months agorvnaresh
4 years, 1 month agorvnaresh
4 years, 1 month ago