Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PRINCE2-Foundation topic 1 question 172 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 172
Topic #: 1
[All PRINCE2-Foundation Questions]

Which level of management sets the project level tolerances?

  • A. Project board
  • B. Team manager
  • C. Corporate, programme management or the customer
  • D. Project manager
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
Reference:
http://prince2.wiki/Manage_by_exception

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Ppp333
6 months, 4 weeks ago
Correct Answer is C. 7.1 The four levels of management: Corporate, programme management or the customer This level sits above the project management team but will be responsible for commissioning the project, including identifying the executive and defining the project-level tolerances within which the project board will work. This information should, if possible, be recorded in the project mandate.
upvoted 1 times
...
Adrienne
7 months ago
Selected Answer: C
C based on 12.2.4
upvoted 2 times
...
RznNsr
8 months ago
Selected Answer: C
The tolerances are set at one level above which they apply and are reported to this level. Corporate or Programme Management set the overall project tolerances. The Project Board is responsible for the project operating within these tolerances.
upvoted 2 times
...
SGN63
1 year, 1 month ago
Selected Answer: C
C is the right answer
upvoted 1 times
...
renza
1 year, 1 month ago
Selected Answer: C
- setting tolerances • Corporate management: set project tolerances • project board: set stage tolerances • project manager agrees with team manager: set workpackages tolerances
upvoted 3 times
...
MrMooMooBee
1 year, 2 months ago
It's C for me!
upvoted 1 times
...
jj0097
1 year, 9 months ago
Selected Answer: C
C is good
upvoted 1 times
...
Nugi
2 years, 9 months ago
Definitely C. ● Corporate, programme management or the customer This level sits above the project management team but will be responsible for commissioning the project, including identifying the executive and defining the project-level tolerances within which the project board will work. This information should, if possible, be recorded in the project mandate.
upvoted 3 times
...
Martin77
3 years ago
C is correct - Corporate, programme management or the customer set the project tolerances (mentioned in section 9.2.2 table 9.1 in the Plans theme and a few other places in the manual)
upvoted 3 times
...
DS001
3 years ago
Corporate, programme management or the customer sets the Project Level Tolerances.
upvoted 4 times
...
Wombat1987
3 years ago
The correct answer is C. https://www.prince2primer.com/project-board-and-project-manager-prince2-controls/ As part of management by exception, corporate or programme management will have set project level tolerances. The project board need to agree stage level tolerances and optionally the project manager may set tolerances at work package level (although this may not need to be done at this point in time).
upvoted 3 times
...
demmy22
3 years, 3 months ago
The answer is Coporate/Programmme. Please you guys should do your research thoroughly before you mislead us. Some answers to the questions seen earlier were wrong.
upvoted 4 times
...
Mehan
3 years, 3 months ago
definitely, it is the corporate, who defines the tolerances level for the projects
upvoted 2 times
...
sohrabiani
3 years, 6 months ago
CPC will set the Project tolerance so accordingly in case of exceeding those tolerances, the case be escalated to them PM will set the work package tolerance
upvoted 2 times
...
Lenlenlen
3 years, 9 months ago
Answer should be C
upvoted 3 times
...
GLKTYI
3 years, 9 months ago
Project board set stage tolerance, project manager set work package tolerance. Corporate program set project level tolerance. So many misleading on these exam practice
upvoted 2 times
...
ejaymac
3 years, 9 months ago
I totally agree this answer is wrong. It is Corporate/Programme that sets the Project tolerance.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...