Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PRINCE2-Foundation topic 1 question 194 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 194
Topic #: 1
[All PRINCE2-Foundation Questions]

What is performed as part of the recommended risk management procedure?

  • A. A budget to investigate issues is allocated
  • B. Risk management practices are reviewed to ensure that they are performed effectively
  • C. Information about risks to the projects is sent to project stakeholders
  • D. Conflicts between the project and the programme board are resolved
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
https://www.greycampus.com/opencampus/prince-2-foundation/prince2-risk-management-procedure

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Wombat1987
Highly Voted 3 years ago
The answer is C. PRINCE2 recommends, but does not mandate, a risk management procedure based on Management of Risk: Guidance for Practitioners (Office of Government Commerce, 2010): Identify (context and risks) Assess (estimate and evaluate) Plan Implement Communicate.
upvoted 9 times
...
DS001
Highly Voted 3 years ago
Answer is C
upvoted 5 times
...
tarikaygul
Most Recent 4 months ago
c is correct
upvoted 1 times
...
PescaruM
4 months, 2 weeks ago
'Issues' is the term used in PRINCE2 for changes therefore I think the answer A is incorrect as it refers to risk management, not change management. Answer C makes more sense.
upvoted 1 times
...
Haranp12
5 months, 2 weeks ago
Selected Answer: C
Should be C. refer 10.4.5 Communication should be undertaken continually. The ‘communicate’ step ensures that information related to the threats and opportunities faced by the project is communicated both within the project and externally to stakeholders.
upvoted 1 times
...
SGN63
1 year, 1 month ago
Selected Answer: C
Should be C
upvoted 3 times
...
KeanoD
1 year, 7 months ago
Selected Answer: C
C seems correct
upvoted 3 times
...
jj0097
1 year, 9 months ago
Selected Answer: C
C is nice
upvoted 2 times
...
peppe
2 years, 6 months ago
C IS CORRECT. "COMMUNICATE"
upvoted 2 times
...
rezab
3 years, 2 months ago
Definitely the answer is C
upvoted 4 times
...
Mehan
3 years, 3 months ago
PRINCE2 MAnual Ref.10.2 ensure that project risks are identified, assessed, managed and reviewed throughout the project lifecycle. I think the correct answer is B. The communication of the risk is part of the Risk management approach, which is also a necessary requirement, but for the approach.
upvoted 1 times
...
Panzerknacker
3 years, 5 months ago
C should be correct as stated in section10.3.2 : 'Communicate', the fith step, operates in parallel as the outputs of any of the other steps may need to be communicted to stakesholders at any point in the process'
upvoted 4 times
...
sohrabiani
3 years, 6 months ago
C Should be correct to communicate the recognized risks with the stakeholders
upvoted 3 times
...
GLKTYI
3 years, 9 months ago
Recommendation risk procedure, Identify, assess, propose, implement and communicate. It should be C
upvoted 3 times
GLKTYI
3 years, 9 months ago
Implement steps is covering implement risk response and reviewed risk response, the correct answered is B
upvoted 3 times
...
...
Prince_Gem
3 years, 10 months ago
I thoughts the answer is C ..where Risk would be communicated.Since there is no minimum requirement for having Budget to investigate issues ?
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...