Exam PRINCE2-Foundation topic 1 question 208 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 208
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is an objective of the 'starting up a project' process?

  • A. To approve the initiation stage
  • B. To select the project mandate
  • C. To define the project quality management approach
  • D. To appoint the project management team
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
http://prince2.wiki/Starting_Up_a_Project#Purpose

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Prince_Gem
Highly Voted 3 years, 10 months ago
I think the answer is D as A is part of Directing by Project Board ?
upvoted 14 times
...
Testeurtest
Highly Voted 8 months, 1 week ago
Selected Answer: D
D is the right answer A. To approve the initiation stage (directing) B. To select the project mandate (before starting up the project and selected by corporate mgmt) C. To define the project quality management approach (initiation) D. To appoint the project management team (starting up)
upvoted 5 times
...
RznNsr
Most Recent 8 months, 1 week ago
Selected Answer: D
D is the right answer
upvoted 2 times
...
renza
1 year, 1 month ago
Selected Answer: D
D is the right answer A. To approve the initiation stage (directing) B. To select the project mandate (before starting up the project and selected by corporate mgmt) C. To define the project quality management approach (initiation) D. To appoint the project management team (starting up)
upvoted 3 times
...
Risto83
1 year, 4 months ago
D 14.2: The objective of the starting up a project process is to ensure that: ● there is a business justification for initiating the project (documented in an outline business case) ● all the necessary authorities exist for initiating the project ● sufficient information is available to define and confirm the scope of the project (in the form of a project brief) ● the various ways the project can be delivered are evaluated and a project approach selected ● individuals are appointed who will undertake the work required in project initiation and/or will take significant project management roles in the project ● the work required for project initiation is planned (documented in a stage plan) ● time is not wasted initiating a project based on unsound assumptions regarding the project’s scope, timescales, acceptance criteria and constraints.
upvoted 1 times
...
lucafranco
2 years, 3 months ago
Corretct answer is D. A. To approve the initiation stage is in DIrecting a project process B. To select the project mandate doesnt have any sense in any process C. To define the project quality management approach is a initiating a process task,
upvoted 2 times
...
Steven2021
2 years, 4 months ago
I would have said A because in chapter 14.1 the very first sentence is this: "The purpose of the starting up a project process is to ensure that the prerequisites for initiating a project* are in place [...]". So *this is an actual stage, therefor I would say A is correct.
upvoted 1 times
...
peppe
2 years, 6 months ago
D is correct
upvoted 1 times
...
Martin77
3 years ago
As per Figure 14.1 Overview of starting up a project (Prince2 guide) appoint the executive and project manager is the first step (which are both part of the Project Management team). D seems to be correct here
upvoted 2 times
Steven2021
2 years, 4 months ago
Sure, but if you look a second time, you'll see that they are only one part of the entire process called "Starting up a project", you see the last output of this process is "Plan the initiation stage", so after this last one so-called "Starting up a project" process is set, the next stage will be started
upvoted 1 times
...
...
DS001
3 years ago
A is part of Directing by Project Board so surely cannot be an answer to this question
upvoted 1 times
...
Wombat1987
3 years ago
The correct answer is D. https://prince2.wiki/processes/starting-up-a-project/ The following Activities are to be done in the Starting Up a Project process: ... Design and appoint the project management team. ...
upvoted 1 times
...
Mehan
3 years, 3 months ago
D is correct
upvoted 2 times
...
sohrabiani
3 years, 6 months ago
D is correct
upvoted 1 times
...
MaximeHU
3 years, 7 months ago
no the starting up a project is made to get into initiation stage.
upvoted 1 times
...
Lenlenlen
3 years, 9 months ago
should be D
upvoted 2 times
...
ejaymac
3 years, 9 months ago
Correct answer is D. A falls under directing a project.
upvoted 2 times
...
Vikce
3 years, 9 months ago
agree, correct answer id D.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...