Exam PRINCE2-Foundation topic 1 question 171 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 171
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is a minimum requirement for applying the quality theme?

  • A. To define the project's approach to quality assurance
  • B. To appoint external reviewers for quality reviews
  • C. To define quality criteria in product descriptions
  • D. To provide administrative support for quality controls
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Lenlenlen
Highly Voted 3 years, 8 months ago
C is correct
upvoted 9 times
...
GetRaj
Highly Voted 3 years, 9 months ago
C seems to be correct
upvoted 5 times
GetRaj
3 years, 8 months ago
Option A is incorrect because as per MSP Reference Its not the To define the project's approach to quality assurance but for Project Assurance
upvoted 3 times
...
GetRaj
3 years, 8 months ago
MSP with Prince2 Reference 8.2 PRINCE2's requirements for quality 2nd point specify explicit quality criteria for products in their product descriptions
upvoted 4 times
...
...
Firey
Most Recent 9 months ago
The Quality theme in project management is concerned with defining and implementing quality standards and processes to ensure that the project's deliverables meet the desired level of quality. "To define quality criteria in product descriptions," is the minimum requirement for applying the Quality theme in project management. Options A, B, and D may be necessary for implementing quality processes, but they are not the minimum requirement for applying the Quality theme.
upvoted 2 times
...
SGN63
1 year, 1 month ago
Selected Answer: C
C is correct
upvoted 2 times
...
jj0097
1 year, 9 months ago
Selected Answer: C
C is correct
upvoted 1 times
...
beti_the_planner
2 years, 4 months ago
both A and C seems correct for me 🙈
upvoted 1 times
...
peppe
2 years, 6 months ago
C is correct
upvoted 3 times
...
Nugi
2 years, 9 months ago
A is correct: define its quality management approach. This approach must minimally cover: ● the project’s approach to quality control ● the project’s approach to project assurance ● how the management of quality is communicated throughout the project lifecycle ● the roles and responsibilities for quality management (PRINCE2’s defined roles and responsibilities principle)
upvoted 5 times
...
Martin77
3 years ago
This is a bit misleading, but C should be correct: reference 8.2 in the prince2 book : Minimum requirements to apply the quality theme : The approach must cover: the project's approach to quality control (not quality assurance). Then: specify explicit quality criteria for products in their product descriptions
upvoted 5 times
...
Farbod
3 years, 1 month ago
C is correct answer. (If A was "quality control" then A would have been correct too, but A is talking about quality assurance)
upvoted 5 times
...
Shanise
3 years, 7 months ago
C is correct.
upvoted 2 times
...
KopytinaN
3 years, 7 months ago
It should be C
upvoted 3 times
...
Petza
3 years, 7 months ago
C is correct according to chapters 8.1 and 8.2
upvoted 3 times
...
Jimeth
3 years, 8 months ago
It's A
upvoted 2 times
...
Lenlenlen
3 years, 8 months ago
A is correct
upvoted 1 times
...
ejaymac
3 years, 9 months ago
Yes. A is correct
upvoted 1 times
...
Vikce
3 years, 9 months ago
i agree with A being correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...