Exam PRINCE2-Foundation topic 1 question 170 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 170
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is a minimum requirement for applying the plans theme?

  • A. The project must have at least two management stages
  • B. The team managers in the project must prepare team plans
  • C. Scope tolerance must be prioritized using MoSCoW
  • D. The project plan must be presented as a Gantt chart
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
http://prince2.wiki/Themes#Plans_Theme

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
GetRaj
Highly Voted 3 years, 9 months ago
Option A is correct
upvoted 16 times
...
GLKTYI
Highly Voted 3 years, 9 months ago
Team plan is optional, not minimum requirement it should be A
upvoted 10 times
...
alir20
Most Recent 3 months, 1 week ago
Selected Answer: A
"A" is the correct answer, as Team plans are not mandatory, however, the 2 stages - "Initializing a project", "Closing a project"
upvoted 2 times
...
Haranp12
6 months, 3 weeks ago
Definitely option A
upvoted 1 times
...
Adrienne
7 months, 1 week ago
Selected Answer: A
"A" is the correct answer, as Team plans are not mandatory, however, the 2 stages - "Initializing a project", "Closing a project" - are.
upvoted 2 times
...
Firey
9 months, 1 week ago
Plans theme minimum requirements: • Ensure that plans enable the business case to be realised, • Have at least 2 management stages: an initiation stage and at least 1 other management stage. The more complex and riskier a project, the more management stages that will be required. • Produce a project plan for the project as a whole and a stage plan for each management stage. • Use product-based planning for the project plan, stage plans and exception plans. • Produce specific plans for managing exceptions. • Define the roles and responsibilities for planning. •Use lessons to inform planning. Definition: Team plan - An optional level of plan used as the basis for team management control when executing work packages. In a PRINCE2 project the team plan is produced by the Team Manager.
upvoted 1 times
...
SGN63
1 year, 1 month ago
Selected Answer: A
should be A
upvoted 1 times
...
Anapellicer
1 year, 1 month ago
Selected Answer: B
B is correct. Team plans are an essential component of the Plans theme, as they detail how specific teams will contribute to the overall project plan. The other options listed may be useful in project management, but they are not specific requirements for applying the Plans theme
upvoted 1 times
...
VJ80
1 year, 4 months ago
pince2wiki is done by a blogger and those cannot be used as reference to choose the answer. as per grey campus the option A is correct and they are recognised institute to train on prince2
upvoted 3 times
...
King_Laps
1 year, 5 months ago
A should be correct here
upvoted 2 times
...
peppe
2 years, 6 months ago
A is correct
upvoted 1 times
...
Mehan
3 years, 3 months ago
100% A is correct
upvoted 5 times
...
AgnesM
3 years, 5 months ago
Definitely answer A is correct..
upvoted 4 times
...
sohrabiani
3 years, 6 months ago
A is correct - The Team plan is not mandatory
upvoted 4 times
...
Jimeth
3 years, 8 months ago
Team plans are not mandatory. Answer is A
upvoted 4 times
...
Lenlenlen
3 years, 9 months ago
should be A
upvoted 5 times
...
GetRaj
3 years, 9 months ago
Refer 9.2 PRINCE2's requirements for the plans theme in MSP Book
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...