Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PRINCE2-Practitioner topic 10 question 4 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner
Question #: 4
Topic #: 10
[All PRINCE2-Practitioner Questions]

Which activity is responsible for updating the stage plan with actual during Controlling a Stage?

  • A. Review the stage status
  • B. Review work package status
  • C. Report Highlights
  • D. Take corrective action
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ManikRoy
6 months, 2 weeks ago
Selected Answer: B
17.4.2 Review work package status Update the stage plan for the current management stage with actuals to date, forecasts and adjustments.
upvoted 1 times
...
ravi_aws
6 months, 2 weeks ago
One of the key activities in the Controlling a Stage process is to review the status of the work packages . Work packages are the smallest units of work in PRINCE2, and they are assigned to team members to complete. By reviewing the status of the work packages, the project manager can gather information on the actual progress made and update the stage plan accordingly.
upvoted 1 times
...
PieroBe
8 months, 4 weeks ago
Selected Answer: B
Ref 17.4.2 (last bullet)
upvoted 1 times
...
MortenC
1 year, 2 months ago
Selected Answer: B
17.4.2 page 221 4th bullet
upvoted 2 times
...
MEHREEN1985
1 year, 4 months ago
C IS CORRECT REF: 17.4.1
upvoted 1 times
MEHREEN1985
1 year, 1 month ago
sorry its B
upvoted 1 times
...
...
timedout
2 years, 7 months ago
A is wrong by default as its missing the word "Management" B is correct "update" Review the management stage status "reviews", but I dont think it "updates"
upvoted 2 times
...
xayay74894
2 years, 8 months ago
Fig. 17.3 pag.221 Review work package status activity cleary updates the stage plan
upvoted 3 times
...
xayay74894
2 years, 8 months ago
Fig. 17.2 pag.219 Authorize a work package activity cleary updates the stage plan
upvoted 1 times
...
Ciluba
3 years, 3 months ago
Should be A. It is a recommended activity of review the management stage status.
upvoted 1 times
...
johnzoids
3 years, 9 months ago
or can be D, take corrective action pg 230 fig 17.9
upvoted 1 times
...
johnzoids
3 years, 9 months ago
update stage plan, is part of the review the management stage status, pg 223 fig 17.5
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...