Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PRINCE2-Practitioner topic 2 question 1 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner
Question #: 1
Topic #: 2
[All PRINCE2-Practitioner Questions]

When updating the project plan as part of Managing a stage boundary, what else might be updated?

  • A. Exception Plan
  • B. Project Management team
  • C. Business Case
  • D. Project Initiation Documentation
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ravi_aws
6 months, 3 weeks ago
C. Business Case
upvoted 1 times
...
chriscilia81
7 months ago
Selected Answer: C
C is the correct answer in my view. True that this goes under the umbrella of the PID, but it can also be a document on its own.
upvoted 1 times
...
ManikRoy
7 months, 1 week ago
I think the correct option is C. Business Case.
upvoted 2 times
...
georgio1974
8 months, 3 weeks ago
Selected Answer: D
D, as the changes to the business case are recorded in the PID
upvoted 1 times
...
ShiroKurtia
8 months, 3 weeks ago
Selected Answer: D
D - PID (in particular in particular the business case, project plan, project approaches, project management team structure and role descriptions" - 19.2 bullet point 3
upvoted 2 times
...
Vijay9
10 months ago
Selected Answer: C
C. Business Case During the "Managing a Stage Boundary" process, the Business Case is one of the key documents that may be updated. It is important to review and update the Business Case to ensure that the project's objectives, benefits, costs, and risks are still valid and align with the current stage and project status. While other elements mentioned (Exception Plan, Project Management team, and Project Initiation Documentation) may require updates in certain scenarios, the Business Case is the most likely element to be updated as part of the "Managing a Stage Boundary" process.
upvoted 4 times
...
Yanju
1 year, 3 months ago
It should be PID
upvoted 1 times
...
ameyaengg
1 year, 7 months ago
Should be Business Case. Refer to page 247 Figure 19.1
upvoted 2 times
...
timedout
2 years, 6 months ago
D - PID (in particular in particular the business case, project plan, project approaches, project management team structure and role descriptions" - 19.2 bullet point 3
upvoted 1 times
...
WikiVicks
2 years, 11 months ago
The activity in the question is 'Update the Project Plan' not 'Update the business case' , so Figure19.1 shouldn't be referred but Figure 19.3. This has PID to be updated
upvoted 2 times
...
Shanise
3 years ago
Should be Business Case. Refer to page 247 Figure 19.1
upvoted 3 times
...
Ciluba
3 years, 3 months ago
PID. Project Plan is part of PID, so PID is definitely being updated.
upvoted 3 times
...
johnzoids
3 years, 9 months ago
Should be PID Pg 251 section 19.4.2
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...