Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.
To be following PRINCE2, a project must, as a minimum:
â—Ź define its approach to controlling progress in the PID
● be managed by stages (PRINCE2’s manage by stages principle)
● set tolerances and be managed by exception against these tolerances (PRINCE2’s manage by
exception principle)
● review the business justification when exceptions are raised (PRINCE2’s continued business
justification principle)
● learn lessons (PRINCE2’s learn from experience principle).
A
12.2:
To be following PRINCE2, a project must, as a minimum:
â—Ź define its approach to controlling progress in the PID
● be managed by stages (PRINCE2’s manage by stages principle)
● set tolerances and be managed by exception against these tolerances (PRINCE2’s manage by
exception principle)
● review the business justification when exceptions are raised (PRINCE2’s continued business
justification principle)
● learn lessons (PRINCE2’s learn from experience principle).
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
GLKTYI
Highly Voted 3Â years, 8Â months agoAgnesM
Highly Voted 3Â years, 4Â months agoKristyna
Most Recent 5Â months, 2Â weeks agoHaranp12
5Â months, 3Â weeks agoTesteurtest
7Â months, 1Â week agoSGN63
1Â year agorenza
1Â year, 1Â month agoRisto83
1Â year, 3Â months agoKing_Laps
1Â year, 4Â months agopeppe
2Â years, 5Â months agoMartin77
2Â years, 11Â months agoTommaso
3Â years, 2Â months agoTommaso
3Â years, 2Â months agoPetza
3Â years, 7Â months agoMehan
3Â years, 2Â months ago