Question #: 216
Topic #: 1
[All PRINCE2-Foundation Questions]

To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?

  • A. At the start of the project
  • B. Throughout each stage
  • C. When a change is raised
  • D. In exception situations
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://www.prince2.com/blog/the-7-principles-themes-and-processes-of-prince2/

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
GetRaj
Highly Voted 3 years, 8 months ago
Option D is correct. As per Prince2 Manual section 12.2 review the business justification when exceptions are raised (PRINCE2's continued business justification principle)
upvoted 8 times
Mehan
3 years, 3 months ago
agree D is the Correct answer
upvoted 3 times
...
...
Testeurtest
Most Recent 8 months ago
Selected Answer: D
I was confused at first but the correct answer is D. https://www.knowledgetrain.co.uk/project-management/prince2/prince2-themes#theme-7 Minimum requirements You must define your project's approach to controlling progress in the project initiation documentation (PID). You must manage by stages, set tolerances and manage by exception against these tolerances. You must review the business justification when exceptions are raised and learn lessons throughout the project.
upvoted 1 times
...
RD27
9 months, 1 week ago
Selected Answer: B
Throughout each stage - Business Justification has to be verified
upvoted 1 times
...
renza
1 year, 1 month ago
Selected Answer: D
D is the right answer
upvoted 1 times
...
peppe
2 years, 6 months ago
D IS CORRECT. BAD QUESTION!!
upvoted 2 times
...
Martin77
3 years ago
To meet the minimum requirements for applying the progress theme - this is the key to this tricky question. 12.2 in the prince manual states (review the business justification when exceptions are raised (PRINCE2's continued business justification principle) ) so D is the correct answer.
upvoted 2 times
...
Wombat1987
3 years ago
I was confused at first but the correct answer is D. https://www.knowledgetrain.co.uk/project-management/prince2/prince2-themes#theme-7 Minimum requirements You must define your project's approach to controlling progress in the project initiation documentation (PID). You must manage by stages, set tolerances and manage by exception against these tolerances. You must review the business justification when exceptions are raised and learn lessons throughout the project.
upvoted 2 times
...
Farbod
3 years, 1 month ago
D is correct "Review the business justification when exceptions are raised."
upvoted 2 times
...
Tommaso
3 years, 3 months ago
B is correct
upvoted 2 times
...
AgnesM
3 years, 5 months ago
Answer D is correct as per section 12.2 in Prince 2 Manual.
upvoted 2 times
...
sohrabiani
3 years, 6 months ago
D is not correct but when exception raise during checking it, the business justification will also be checked
upvoted 3 times
...
MaximeHU
3 years, 7 months ago
yes but also at each stages wich is more important.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...