Exam PRINCE2-Foundation topic 1 question 174 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 174
Topic #: 1
[All PRINCE2-Foundation Questions]

If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be reduced or eliminated?

  • A. Appointing the project board and producing the project brief
  • B. Planning the initiation stage and appointing the project manager
  • C. Producing the additional role descriptions and validating the project product description
  • D. Verifying the project approach and capturing previous lessons
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
http://prince2.wiki/Starting_Up_a_Project#Activities

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
[Removed]
Highly Voted 1 year, 10 months ago
A is correct, 13.3: Context The effort involved in starting up a project will vary enormously from project to project. If the project is part of a programme, the programme itself should provide the project brief and will appoint some, if not all, members of the project board, thus eliminating much of the work required in this process. In such cases, the project manager should validate what is provided by the programme and, if necessary, recommend modifications.
upvoted 6 times
...
Firey
Most Recent 8 months, 1 week ago
https://www.exam-answer.com/starting-up-project-reduce-eliminate
upvoted 1 times
...
SGN63
1 year ago
Selected Answer: A
I think it should be A
upvoted 2 times
...
knowlathon1
2 years, 3 months ago
To solve all your queries regarding Prince2 certification, you can explore these project management Certifications courses: https://www.knowlathon.com/project-management/prince2-agile-foundation-bangalore/ https://www.knowlathon.com/project-management/prince2-agile-certification/
upvoted 1 times
...
Rahu
2 years, 3 months ago
Correct answer is D Please refer 6.3.4 in page 54 If the project is part of a programme, the programme will typically define both the approach to business case development and provide an outline business case for the project.
upvoted 1 times
...
peppe
2 years, 5 months ago
A is correct pg 167
upvoted 1 times
...
Martin77
2 years, 11 months ago
I think C is the answer here, as per 14.5.4.4 from the Prince2 manual - the programme manager should ensure the appointment of the executive and project manager, prepare the project brief, alert the project manager to any relevant previous lessons and ensure an initial project management team is appointed.
upvoted 1 times
...
Wombat1987
2 years, 12 months ago
The correct answer is D. Verifying the project approach and capturing previous lessons You do not need to verify the project approach as it has been already done on the Programme level within Project Brief preparation: https://prince2.wiki/processes/starting-up-a-project/ During this process, the project mandate will be expanded into the Project Brief. Keep in mind that the Project Brief will be used by the Project Board to decide whether to Initiate the project or not. Note: if the project is part of a program, then the program will provide most of the Project Brief. In fact, most of the work in this process will already be done by the program.
upvoted 4 times
...
demmy22
3 years, 2 months ago
A is correct
upvoted 1 times
...
kellysmithdec2020
3 years, 3 months ago
Definition from http://prince2.wiki/ seems wrong on all suggested answers.
upvoted 2 times
...
Panzerknacker
3 years, 4 months ago
I thinkk A. is wrong. in Section 14.5.4.4 it says: "In any case, the programme manager should ensure the appointment of the executive and project manager, prepare th eproject brief,..."
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...