Exam PRINCE2-Foundation topic 1 question 238 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 238
Topic #: 1
[All PRINCE2-Foundation Questions]

Which process monitors work that has been assigned to a team manager?

  • A. Controlling a stage
  • B. Directing a project
  • C. Managing a stage boundary
  • D. Managing product delivery
Show Suggested Answer Hide Answer

Suggested Answer: D
Reference -
https://www.whatisprince2.net/prince2-process-managing-product-delivery.php

Comments

dboy711
2 days, 10 hours ago
Shouldn't this be "Controlling a Stage" Process instead? The purpose of the Controlling a Stage process (CS) is for the Project Manager to assign the work to be done, monitor this work, deal with issues, report Progress to the Project Board and take corrective action to ensure that the stage remains within tolerance.
upvoted 1 times
...