Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PRINCE2-Practitioner topic 9 question 21 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner
Question #: 21
Topic #: 9
[All PRINCE2-Practitioner Questions]

During stage 3, the team manager reports that the work to update the 'corporate quality procedures' has been completed and the product is ready to be delivered.
What should project assurance do next?

  • A. Update the team plan to show that the work package is complete.
  • B. Check the work package and follow the procedure to deliver completed products.
  • C. Verify that all the products to be delivered by the work package are approved.
  • D. Update the stage plan to show the work package as completed.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ravi_aws
6 months, 2 weeks ago
In PRINCE2, the role of project assurance includes ensuring that the products produced by the work packages are of the required quality and meet the defined criteria for approval. Therefore, when the team manager reports that the work to update the 'corporate quality procedures' has been completed and the product is ready to be delivered, the project assurance should verify that all the products to be delivered by the work package have been reviewed and approved before they are formally accepted and used in the project.
upvoted 1 times
...
anti8
2 years, 3 months ago
18.4.3
upvoted 2 times
...
lovelifeysl_2021
2 years, 5 months ago
I THINK IT IS C
upvoted 1 times
...
sunee
3 years ago
c is correct
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...