Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.
This one is tricky.
D is wrong because the directing a project process starts on completion of the starting up a project process and is triggered by the request(!), not completion, to initiate a project.
Therefore A is correct: The directing a project process provides a mechanism for the project board to meet its responsibility for ensuring that there is continued business justification without being overburdened by project activity.
The directing a project process covers the activities of the project board and is not concerned with the day-today activities of the project manager.
upvoted 3 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Jasonbahr
Highly Voted 3 years agoa2d1fd1
Most Recent 1 week, 3 days ago[Removed]
1 year, 11 months ago