Which is an objective of the `˜controlling a stage' process?

  • A. To review the business justification for the project
  • B. To replan the current stage when directed
  • C. To develop products to defined quality criteria
  • D. To produce a team plan for the work package
Show Suggested Answer Hide Answer

Suggested Answer: D
Reference:
https://www.greycampus.com/opencampus/prince-2-practitioner/activities-in-controlling-stage-process-in-prince2

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
beti_the_planner
1 week, 4 days ago
Selected Answer: A
why so many mistakes
upvoted 1 times
...
peppe
1 month, 2 weeks ago
A is correct
upvoted 1 times
...
myousefi
2 months, 2 weeks ago
A is correct ,
upvoted 1 times
...
theotenis
6 months, 4 weeks ago
Correct answer is B.
upvoted 1 times
...
Most Voted