Exam PRINCE2-Foundation topic 1 question 316 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 316
Topic #: 1
[All PRINCE2-Foundation Questions]

According to the 'tailor to suit the project' principle, what is the basis for effective project management?

  • A. That the appropriate number and type of meetings are held
  • B. That the project is divided into an appropriate number of stages
  • C. That the appropriate information is provided to make decisions
  • D. That the right people are involved in appropriate roles
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
Reference:
https://prince2.wiki/principles/tailor-to-suit-the-project-environment/

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Martin77
Highly Voted 2 years, 11 months ago
This is wrong. C is correct. Reference Prince2 guide - 3.7 - When tailoring PRINCE2, it is important to remember that effective project management requires information (not necessarily documents) and decisions (not necessarily meetings).
upvoted 6 times
...
jj0097
Most Recent 1 year, 9 months ago
D is correct
upvoted 1 times
...
AliSami
1 year, 11 months ago
C is the correct answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...