Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PRINCE2-Foundation topic 1 question 122 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 122
Topic #: 1
[All PRINCE2-Foundation Questions]

Which document should record the agreed amount of risk budget for a project?

  • A. Project Brief
  • B. Project Plan
  • C. Risk Management Strategy
  • D. Risk Register
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
KeanoD
Highly Voted 1 year, 7 months ago
Selected Answer: B
I go for B - in the main Project plan. PRINCE2 recommends the following are included in the budget for a plan: 1.money to fund the activities to create specialist products (and management activities) 2.money to fund responses to risks (risk budget) 3. money to fund authorized changes to baseline products (change budget) 4. cost tolerance
upvoted 7 times
...
renza
Most Recent 1 year, 1 month ago
Selected Answer: B
• Risk Management Strategy will detail if a risk budget is to be used, what it will be used for, and defines mechanisms for control of and access to this budget • Amounts are documented in the relevant plan
upvoted 1 times
...
ArifNazin
1 year, 2 months ago
Selected Answer: B
Given it is part of project budget, it will be in Project Budget, which will be added to project plan. hence B
upvoted 1 times
anstpl
1 year, 2 months ago
The project BUDGET but the project PLAN. So the answer is C (not B the Project Plan)
upvoted 1 times
...
...
Risto83
1 year, 4 months ago
B As the risk budget is part of the project budget
upvoted 1 times
...
King_Laps
1 year, 5 months ago
The correct answer is C
upvoted 2 times
...
jj0097
1 year, 9 months ago
Selected Answer: C
C is good
upvoted 1 times
...
natavorc
1 year, 10 months ago
page 125 ;10.3.7 Establishing a risk budget => As the risk budget is part of the project budget, there may be a tendency to treat it as just another sum of money that the project manager can spend .
upvoted 1 times
...
skanasu
2 years, 1 month ago
Selected Answer: C
c is correct
upvoted 1 times
...
Goseu
2 years, 4 months ago
Selected Answer: C
C seems corrext
upvoted 1 times
...
peppe
2 years, 6 months ago
C is correct
upvoted 1 times
...
hatachino1
2 years, 7 months ago
A Risk Budget is a sum of money that is put aside just to deal with specific responses to threats or opportunities and it cannot be used for anything else. Risk Budget is often referred to as a contingency budget and defined in the Rish Management Approach document. So the correct answer should be C!
upvoted 1 times
...
Dr34mt1m3
2 years, 9 months ago
Risk budget is reserved in Risk Management Strategy and so it should be C
upvoted 1 times
...
Nugi
2 years, 9 months ago
Shouldn't it be C? A risk management approach describes how risk will be managed on the project. This includes the specific processes, procedures, techniques, standards and responsibilities to be applied.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...