Exam PRINCE2-Foundation topic 1 question 24 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 24
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is a purpose of the Controlling a Stage process?

  • A. Produce a Team Plan for the work to be assigned to a Team Manager
  • B. Select and implement actions that will resolve deviations from a plan within tolerance
  • C. Obtain approvals for products delivered in a Work Package
  • D. Update a Project Plan to incorporate the actuals from a Stage Plan
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
test235
4 months ago
Selected Answer: B
B is correct, take corrective action
upvoted 1 times
...
mr_alok
1 year, 1 month ago
Selected Answer: B
B is correct The purpose of the Controlling a Stage process (CS) is for the Project Manager to assign the work to be done, monitor this work, deal with issues, report Progress to the Project Board and take corrective action to ensure that the stage remains within tolerance.
upvoted 2 times
...
peppe
2 years, 6 months ago
B is correct: take corrective action
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...