Which is a purpose of the ‘initiating a project’ process?

  • A. To ensure the project has a sound basis before asking the project board to authorize the project
  • B. To authorize the stage plan for the next management stage of the project
  • C. To establish a contract between the project management team and the commissioning organization
  • D. To ensure that prerequisites are in place before starting the project
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Examcollectorthanos
2 weeks, 1 day ago
A is correct; Why other options are not the primary purpose: B. To authorize the stage plan for the next management stage of the project: This happens at the end of each stage, not during the initial initiation. C. To establish a contract between the project management team and the commissioning organization: While contracts might be involved, the primary focus is on establishing a sound basis for the project itself. D. To ensure that prerequisites are in place before starting the project: This is part of the "starting up a project" process, which follows "initiating a project."
upvoted 1 times
...
Kjennset
1 month ago
Selected Answer: A
The primary purpose of the 'Initiating a Project' process in PRINCE2 is to ensure that there is a solid foundation for the project before seeking authorization from the Project Board to proceed. This process involves developing detailed plans, defining the project scope, assessing risks, and preparing the Project Initiation Documentation (PID) to give the Project Board confidence that the project is viable and properly planned before they approve its launch.
upvoted 1 times
...
Toyeeb
7 months ago
Selected Answer: A
15.1 Purpose The purpose of the process of initiating a project is to establish solid foundations for the project, enabling the business to understand the work that needs to be done to deliver the project product before committing to any significant expenditure or resources.
upvoted 1 times
...
Darkvirusk
1 year, 8 months ago
I think it should be D
upvoted 1 times
...
Ro96
1 year, 11 months ago
A should've been done in the starting phase, the answer is wrong
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...