Exam PRINCE2-Foundation topic 1 question 443 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 443
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is a purpose of the ‘initiating a project’ process?

  • A. To ensure the project has a sound basis before asking the project board to authorize the project
  • B. To authorize the stage plan for the next management stage of the project
  • C. To establish a contract between the project management team and the commissioning organization
  • D. To ensure that prerequisites are in place before starting the project
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Darkvirusk
1 year, 1 month ago
I think it should be D
upvoted 1 times
...
Ro96
1 year, 4 months ago
A should've been done in the starting phase, the answer is wrong
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.