Universal Containers wants to ensure that Service Appointments are only assigned to Active Resources. What configuration should a Consultant recommend for the Scheduling Policy?
Wrong answer - They should use the Work Rule: "Active Resources" Which considers only active Service Resources when scheduling.
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
givagr
1 year, 2 months agoRichy1000
2 years, 7 months agoRick1234
3 years, 2 months agokennyrogers
3 years, 2 months agomwoodbridge
3 years, 5 months ago