Exam PSM II topic 1 question 4 discussion

Actual exam question from Scrum's PSM II
Question #: 4
Topic #: 1
[All PSM II Questions]

Paul, a Product Owner of one of the Scrum Teams, has been attending the Daily Scrum. During the Daily Scrum, the Development Team members have been reporting their daily work to Paul so that he is aware of their Sprint progress and what each member is working on.
What is the best action for the Scrum Master to take?

  • A. Ask Paul to stop attending the Daily Scrum.
  • B. Coach Paul and Development Team members on the purpose of the Scrum events and let them figure out what to do in this situation.
  • C. Allow the Paul to participate in the Daily Scrum as he is responsible for the success of the product.
  • D. Facilitate the Daily Scrums to avoid any conflicts between the Development Team members and Paul.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Because the Development Team is the ones doing the work, they are best suited to inspect and adapt the progress toward the Sprint Goal. At minimum, this is done every 24 hours through the Daily Scrum. It is the Scrum Master's responsibility to teach the Scrum Team the value and objective of each Scrum event in order for them to optimize the benefits of each event. Because the Daily Scrum is owned by the Development Team, it is up to them on how they should run it but the Scrum Master can provide guidance to ensure it adheres to the Scrum guidelines.

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
PaulWaltR
4 months, 2 weeks ago
Has to be B. Paul should attend Daily Scrum if he is a "Dev" other PO is not required to atted Daily. It a Dev event.
upvoted 1 times
...
kikakiko
3 years ago
Answer cant be B.
upvoted 1 times
EricSon
2 years, 11 months ago
B is the best answer. The explanation is reasonable as well, PO can still attend the Daily Scrum where appropriate, if they understand the purpose of the Scrum events.
upvoted 1 times
...
...
amog
3 years, 1 month ago
Answer is B
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.