Scenario -
Your role is that of a consultant to the Lead Enterprise Architect in a company that develops photovoltaic technologies for use in large-scale solar power farms.
The company has three manufacturing facilities, two in the United States, and one in Southern France. Each of these facilities supplies a different manufacturer that assembles and sells complete systems. The solar panels and photovoltaic arrays are custom engineered to meet each manufacturer's design specifications.
A challenge that the solar power industry has faced is the efficiency of energy conversion. When a conventional solar panel overheats, it becomes inefficient and generates less energy. In response to this, the research arm of the company has pioneered the development of a new solar panel design that will produce up to
50% more energy than standard solar panels when operating at elevated temperatures. This will allow the production of significantly more useable energy per square meter than from standard solar technology. This new design is ready to go into production.
The company has a mature Enterprise Architecture practice that is supported by a cross-functional Architecture Board. TOGAF 9 is used for developing the automated manufacturing process and systems used to design, manufacture and test the solar power technologies they produce. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
As part of putting the new solar panel design into production, a pilot architecture project at a single location has defined an updated standard approach for controlling the automated test systems used to perform final quality assurance. The Chief Engineer, sponsor of the activity, and the Architecture Board have approved the plan for immediate implementation at each plant.
Architecture Contracts have been developed that detail the work needed to implement and deploy the new automated test system controller for each location. The
Chief Engineer has expressed concern that a uniform process be employed at each location to ensure consistency and high yields.
The Lead Enterprise Architect has asked you to recommend the best approach to address the Chief Engineer's concern.
Based on TOGAF, which of the following is the best answer?

  • A. You review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management. In cases where the contract is issued to an external party, you ensure that it is a legally enforceable contract. You schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architecture Definition. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
  • B. You create an Architecture Contract to manage and govern the implementation and migration process at each location. For internal development projects, you issue a memorandum of understanding between the Architecture Board and the implementation organization. For contracts issued to an external party, you ensure that it is a fully enforceable legal contract. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
  • C. You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Architecture Board and the implementation organization. You recommend that if a deviation from the Architecture Contract is detected, the Architecture Board grant a dispensation to allow the implementation organization the ability to customize the process to meet their local needs.
  • D. You use the Architecture Contracts to manage the architecture governance processes for the project across the locations. You deploy monitoring tools to assess the performance of each completed solar panel assembly at each location and develop change requirements if necessary. You recommend that if a deviation from the contract is detected, the Architecture Board should modify the Architecture Contract to allow the implementation organization the ability to customize the process to meet their local needs. As a result, you then issue a new Request for Architecture Work to implement the modified Architecture Definition.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
b4c
Highly Voted 3 years, 10 months ago
This answer doesn't seem right. After all, the contracts have been already created. Answer A seems a better answer for this scenario
upvoted 18 times
Victor6510
3 years, 7 months ago
Ans A doesn't enforce a consistent and single Architecture Contract.
upvoted 4 times
...
susridey
2 years, 9 months ago
Completely agree, the contracts are already developed so that's the indication that it just needs to be reviwed, and then any deviation needs to be reviewed by ARB
upvoted 1 times
...
Indranee
3 years, 1 month ago
Agree with A being the better answer. 1. "Architecture Contracts have been developed that detail the work needed " -> Contracts have already been created, so why are we creating contracts again in B and C? Therefore I went with A. 2. "a uniform process be employed at each location to ensure consistency and high yields" -> Maybe this is the reason why in option A, "You review the applicable Architecture Contract for each location" and "compliance reviews"
upvoted 6 times
...
...
tomvik
Highly Voted 3 years, 9 months ago
Answer is B
upvoted 7 times
Victor6510
3 years, 7 months ago
Agreed. Should be Ans B.
upvoted 2 times
...
...
Watad
Most Recent 1 year, 1 month ago
Selected Answer: A
repeated, see Question #17
upvoted 3 times
...
mericov
1 year, 7 months ago
Selected Answer: B
18.4? Two approaches can be adopted within the ADM for the development of architectures: ■ Baseline First: This process is most suitable when the baseline is complex, not clearly understood, or agreed upon. This approach is common where organizational units have had a high degree of autonomy. ■ Target First: This process is suitable when a target state is agreed at a high level and where the enterprise wishes to effectively transition to the target model
upvoted 1 times
...
tushmish
2 years ago
Selected Answer: A
same as 9, 17, 52, 69
upvoted 3 times
0xE8D4A51000
1 year, 3 months ago
why do they repeated the question in the question bank? it's so annoying and they're pretending they have more questions when there a quite a few duplicates!
upvoted 1 times
Skittle4710
1 year, 2 months ago
More importantly, why do they post different correct answers for the same exact question?
upvoted 1 times
...
...
...
KMurthy04
2 years, 8 months ago
I think its D, because inone of the old Question paper it was "D". and all the other options says - create Arch Contract, or Review Arch contract, but in the question it seems like Arch contract is already done. So we need to "use" the arch contract, there fore the Answer must be D
upvoted 2 times
...
sameersoftyhcl
2 years, 10 months ago
In Answer C, if there is a deviation found and Architecture board grants the dispensation to customize process for their local need, how will it ensure consistency? I think right answer is A, because the same has been marked as answer in Q 17.
upvoted 2 times
...
pankaj3284
3 years, 1 month ago
Answer is A , there is no term like MOU(Memorandom of Understanding) in Togaf
upvoted 7 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...