Exam VCS-277 topic 1 question 33 discussion

Actual exam question from Veritas's VCS-277
Question #: 33
Topic #: 1
[All VCS-277 Questions]

An administrator has a scheduled policy that backs up 20 clients, each with multiple mount points and multiple data streams enabled. One of the jobs has failed and is in an Incomplete state in the Activity Monitor.
How should the administrator verify the incomplete job runs prior to the next scheduled backup?

  • A. run a manual job for the client
  • B. resume the job
  • C. run a manual job for the mount point
  • D. resume the parent job
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
fmatzinger
3 years, 1 month ago
you can't resume a failed job, you can only restart it
upvoted 1 times
Swanie
2 years, 1 month ago
The job i not failed totally. It is in an incomplete state and thus can be resumed. Correct answer is thus B
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...