74-343 Actual Exam Questions

Last updated on Nov. 25, 2024.
Vendor:Microsoft
Exam Code:74-343
Exam Name:Managing Projects with Microsoft Project 2013
Exam Questions:101
 

Topic 1 - Single Topic

Question #1 Topic 1

Your organization uses Project Professional 2013 and records actual hours worked on the project.
You manage a small e-commerce website implementation project. One of your testers asks for assistance in completing a critical task, and you find two additional testing resources that can assist with executing the critical test cases.
The total estimated work for the effort-driven task is 100 hours. The original testing resource, Resource1, completes 25 hours of work on the task.
You need to add Resource2 and Resource3 to the task and split the remaining hours across all three resources now working on the task.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

  • A. Open the Task Form and format it to show Work Details. Enter 25 hours of actual work for Resource1. Then save the changes.
  • B. Open the Task Form and format it to show Work Details. Enter 75 hours of remaining work for the assigned resource. Then save the changes.
  • C. Assign Resource2 and Resource3 to the task. Then save the changes.
  • D. Open the Task Form and format it to show Work Details. Enter 33.33 hours of work for each resource. Then save the changes.
Reveal Solution Hide Solution   Discussion  

Correct Answer: AC 🗳️

Question #2 Topic 1

You are managing a project using Project Professional 2013.
Your project schedule is showing task overallocation indicators in the Gantt chart view. You navigate to the Team Planner view to investigate more details regarding the over allocations.
You discover that the BA1 resource is overallocated and you need to see all assignments with details for BA1 to understand their current workload before making any assignment changes.
What should you do?

  • A. Click the BA1 resource and scroll to the end of the project.
  • B. Click View, check Details, select Resource Form then click on the BA1 resource.
  • C. Click View, check Details, select Task Form then click on the BA1 resource.
  • D. Right-click the BA1 resource and select Information.
Reveal Solution Hide Solution   Discussion  

Correct Answer: B 🗳️

Question #3 Topic 1

You are a project manager who uses Project Standard 2013.
You are creating a preliminary project schedule and are estimating the number of resources required prior to finalizing the schedule. You do not have named resources to complete the tasks, but you know the resource roles that are necessary. One of the roles needed is architect.
You need to estimate how many architect hours are required to complete the work.
What should you do?

  • A. Add a Material Resource named architect.
  • B. Add a Budget Resource named architect.
  • C. Add a Work Resource named architect,
  • D. Add a Cost Resource named architect.
Reveal Solution Hide Solution   Discussion  

Correct Answer: C 🗳️

Question #4 Topic 1

Your company uses Project Professional 2013.
You are setting up a preliminary schedule by using manually scheduled tasks. You create a task with no duration, start, or finish date, and then you assign a resource. Later, you enter a duration of three days for that task.
You need to let the resource know how the Work will be affected.
What should you say?

  • A. Work will increase to 24 hours.
  • B. Work will remain at 0 hours.
  • C. Work will increase to 16 hours.
  • D. Work will remain at 8 hours.
Reveal Solution Hide Solution   Discussion  

Correct Answer: A 🗳️

file Viewing page 1 out of 26 pages.
Viewing questions 1-4 out of 101 questions
Next Questions
Browse atleast 50% to increase passing rate cup
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago