Question #1 Topic 1

Which product records any project outcomes perceived as negative by stakeholders?

  • A. Business Case
  • B. Project Plan
  • C. Communication Management Strategy
  • D. Project Product Description
Reveal Solution Hide Solution   Discussion   13

Correct Answer: A 🗳️

Question #2 Topic 1

What is the definition of a project outcome?

  • A. A measurable improvement that is perceived as an advantage by one or more stakeholders
  • B. The reason for the project
  • C. The result of the change derived from using the project's outputs
  • D. The project's specialist products.
Reveal Solution Hide Solution   Discussion   6

Correct Answer: C 🗳️

Question #3 Topic 1

Which is NOT a purpose of a Benefits Review Plan?

  • A. Define the period over which the cost-benefit analysis will be based
  • B. Describe how to measure the performance of the project's products in operational use
  • C. Define the scope, timing and ownership of the benefit reviews required
  • D. Describe how to measure and confirm any benefits that are to be realised after the project is closed
Reveal Solution Hide Solution   Discussion   6

Correct Answer: A 🗳️

Question #4 Topic 1

Which product documents the information needed to demonstrate continued business justification?

  • A. Business Case
  • B. Communication Management Strategy
  • C. Project Product Description
  • D. Quality Management Strategy
Reveal Solution Hide Solution   Discussion  

Correct Answer: A 🗳️

Question #5 Topic 1

Which is NOT a purpose of a Benefits Review Plan?

  • A. Define the period over which the cost-benefit analysis will be based
  • B. Describe how to measure the performance of the project's products in operational use
  • C. Define the scope, timing and ownership of the benefit reviews required
  • D. Describe how to measure and confirm any benefits that are to be realised after the project is closed
Reveal Solution Hide Solution   Discussion   3

Correct Answer: A 🗳️

Question #6 Topic 1

What is an off-specification?

  • A. A new requirement
  • B. A quality tolerance
  • C. A type of issue
  • D. A major risk
Reveal Solution Hide Solution   Discussion   4

Correct Answer: C 🗳️

Question #7 Topic 1

Which is a type of issue?

  • A. A lesson
  • B. A request for change
  • C. An Exception Report
  • D. A risk with an estimated high impact
Reveal Solution Hide Solution   Discussion   2

Correct Answer: B 🗳️

Question #8 Topic 1

Which is a typical core activity within configuration management?

  • A. Quality assurance
  • B. Risk management
  • C. Verification and audit
  • D. Progress reporting
Reveal Solution Hide Solution   Discussion   3

Correct Answer: C 🗳️

Question #9 Topic 1

Which is a typical core activity within configuration management?

  • A. Issue management
  • B. Quality inspection
  • C. Identification
  • D. Preparation
Reveal Solution Hide Solution   Discussion   3

Correct Answer: C 🗳️

Question #10 Topic 1

What needs to be in place to ensure effective issue and change control?

  • A. Configuration management system
  • B. Manage by exception
  • C. Quality planning
  • D. Information needs for stakeholders
Reveal Solution Hide Solution   Discussion   1

Correct Answer: A 🗳️

Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...